CLE 036 Engineering Change Proposals 2025 Complete Practice Test

Question: 1 / 400

Who typically reviews and approves an ECP?

A single project manager

An external consultant

A cross-functional team

The review and approval of an Engineering Change Proposal (ECP) is typically conducted by a cross-functional team. This is because an ECP can impact various aspects of the project, including design, manufacturing, quality assurance, and supply chain management. Involving a diverse group of stakeholders ensures that all potential effects of the proposed change are considered and evaluated comprehensively.

A cross-functional team usually consists of members from different departments, such as engineering, procurement, production, and marketing. Each member brings their unique perspective and expertise, which helps in assessing the feasibility, implications, and costs associated with the proposed change. This collaborative approach leads to a more informed decision-making process and minimizes the risks associated with implementing changes.

While it may seem practical for a single project manager to approve changes, doing so could overlook vital insights from other areas of the project. External consultants may offer valuable input but are not typically involved in the routine approval process. Similarly, confining the review to only the engineering team restricts the diverse input needed to evaluate the broader impact of an engineering change. Thus, a cross-functional team is essential for the effective review and approval of an ECP.

Get further explanation with Examzify DeepDiveBeta

Only the engineering team

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy